Forcing molten metal under high pressure into reusable steel dies to produce parts with excellent dimensional stability and fast production cycles.
| Stage | Activities | Timeline |
|---|---|---|
| 01 Inquiry & Quotation | Drawing review, DFM analysis, material recommendation, cost estimation | 1-3 business days |
| 02 Engineering Review | Tolerance analysis, tooling design, process planning, prototype confirmation | 3-5 business days |
| 03 Mold & Tooling | Mold manufacturing, first article inspection (FAI), customer sample approval | 15-25 days |
| 04 Mass Production | Casting, machining, surface treatment, in-process quality control | 20-35 days |
| 05 Final QC & Packing | 100% dimensional inspection, performance testing, anti-rust packaging | 3-5 days |
| 06 Logistics & Delivery | FOB / CIF / DDP shipping, customs documentation, tracking updates | By sea 20-35 days |